(Danakali)Danakali Releases Quarterly Report For Period Ending September 30, 2015

From: Semere Asmelash <semereasmelash_at_ymail.com_at_dehai.org>
Date: Thu, 29 Oct 2015 05:40:30 +0000 (UTC)

http://www.asx.com.au/asxpdf/20151029/pdf/432hrkp1pbg18t.pdf


Danakali Releases Quarterly Report For Period Ending September 30, 2015

HIGHLIGHTS

COLLULI POTASH PROJECT

Definitive Feasibility Study well advanced and on track for Q4 2015 release


Completion of the piloting and variability trials confirm robustness of the process plant design

Generation of 300 kg of Colluli SOP product in Soluble, Standard and Granular form

347 million tonne rock salt resource estimate announced

60% reduction in process plant water requirements

High potassium process water identified on site

Large subsurface aquifer identified at the Colluli site – has the

potential to completely eliminate the 75km seawater delivery pipeline from Anfile Bay

Detailed mine scheduling well advanced

Successful completion of compaction trials

Colluli Exploration License renewal complete

Danakali represented at The Fertiliser Institute (TFI) World Fertiliser

Conference in Boston

PLANNED FOR DECEMBER QUARTER

Completion of Colluli Definitive Feasibility Study

Completion of Social and Environmental Impact Assessments and Management Plans

Initiation of Mining Agreement submission

Continuation of dialogue with potential customers, progressing towards offtake agreements

Continuation of project debt funding dialogue

CORPORATE

Cash position of A$5.108M at end September

Board &amp; Management continue to grow shareholding

New website and project video launched

Share registry changed to Computershare