| Jan-Mar 09 | Apr-Jun 09 | Jul-Sept 09 | Oct-Dec 09 | Jan-May 10 | Jun-Dec 10 | Jan-May 11 | Jun-Dec 11 |

[dehai-news] Proactiveinvestors.co.uk: South Boulder Mines steps on the gas towards its transition to potash producer in Eritrea

From: Berhane Habtemariam <Berhane.Habtemariam_at_gmx.de_at_dehai.org>
Date: Wed, 11 Jan 2012 13:27:09 +0100

South Boulder Mines steps on the gas towards its transition to potash
producer in Eritrea


Wednesday, January 11, 2012 by Angela Kean

 <http://eastafro.com/Post/wp-content/uploads/2012/01/colpotash.jpg>
http://eastafro.com/Post/wp-content/uploads/2012/01/colpotash.jpgHighly
favourable economics for the Colluli Potash Deposit in Eritrea have allowed
South Boulder Mines to expedite the transition to potash production in 2016
or even sooner. The company is also strengthening its cash position with a
A$10.7 million capital raising that will increase its bank balance to $21
million in early February.

South Boulder Mines (ASX: STB) is making strong progress towards the
completion of a Definitive Feasibility Study (DFS) for the development of
its Colluli Potash Deposit, with all key technical activities to complete
the study in 2013 underway or set to begin in the near term pending
approvals.

The company recently received some highly favourable economics from
discounted cash flow financial modelling for the base case Stage 1 open pit
mining and processing of the Colluli Potash Deposit including a net present
value of US$1.33 billion and an internal rate of return of 40.6%.

South Boulder Mines is planning a series of investor visits starting this
month to assess potential financial, offtake and development partners for
the Colluli Project.

Importantly for the resource at Colluli, some of the resource sits in the
higher confidence categories, with 133.7 million tonnes at 17.55% KCl in the
Measured category, 343.3 million tonnes at 17.38% KCl in the Indicated
category, and 87.3 million tonnes at 24.96% KCl in the Inferred category.

The company has provided the market with an update on recent key activities
and highlights from Collulli.

- Potash assays from a further six resource extension holes were returned
from holes completed in the last drill program. An updated JORC Resource
estimate is planned for completion in the March quarter;

- A program of HQ diamond drilling has recommenced, with five holes
completed to date, to define further shallow potash. Continuous drilling is
planned throughout the next 14 months, beginning with an initial resource
extension program of 22 holes for 2,000 metres;

- A close spaced (50-200 metres centres) PQ diamond drilling program is in
the final stages of approval. Up to 70 holes will be completed to collect
sufficient samples for definitive metallurgical testing and to assess the
short range variability and localised geometry of the deposit;

- A total of 13 hydrogeological monitoring bores have been installed at Area
A as part of DFS ground water and geotechnical assessment with respect to
open cut mining studies;

- South Boulder Mines has begun a global tender process for DFS engineering
design and is expecting to award the tender in February 2012;

- The recently completed Engineering Scoping Study produced a pre-tax net
present value of US$1.33 billion with start-up capital costs of US$0.74
billion based on production of an initial 1 million tonnes of KCl per annum.


The study only considered 20% utilisation of the current resource and
therefore enormous upside is expected.

- South Boulder is well funded to complete the DFS and is in the process of
completing a fully underwritten 1 for 5 Entitlement Issue to raise about
$10.7 million. This will result in a strong cash position of $21 million in
early February.

Approvals Pending

Key activities currently awaiting approvals include:

- A close spaced PQ diamond drilling program (similar to a broadly spaced
grade control program) is in the final design and approval stages to assess
the short range variability of the deposit with respect to mining methods,
assist with ongoing geological interpretation of the deposit and to collect
sufficient potash samples for definitive feasibility processing test work.

It is planned that the program will be undertaken over potential mining
areas that correspond to the first few years of production from Area A;

- A complete Social Environment Impact Assessment plan has been submitted to
the Eritrean Government for consideration. Approval of the plan is
anticipated in the March quarter and a number of data collection activities
are well underway to support the DFS;

- A Baseline Hydrology Program was initiated in November 2011 and included
the installation of 13 hydrogeological monitoring bores at Area A. Initial
assessment was made at Colluli and adjacent regional areas to plan the
ongoing surface and ground water assessment programs.

 






         ----[Mailing List for Eritrea Related News ]----

image001.jpg
(image/jpeg attachment: image001.jpg)

Received on Wed Jan 11 2012 - 10:08:46 EST
Dehai Admin
© Copyright DEHAI-Eritrea OnLine, 1993-2012
All rights reserved